Posted on: September 3, 2019

[ARCHIVED] Hwy. 60 Project - Week 21: Phase One's permanent striping set for Monday

Hwy. 60

The City of Faribault and its project partners intend to send out and publish a weekly construction update on the Trunk Highway 60/4th Street NW Reconstruction Project. To receive the newsletter, see instructions at the bottom of this post. 

Previous Week Review  8/31/19-9/6/19

Watermain and sanitary sewer utility work was completed in the 700 block up to 8th Avenue NW. Storm sewer, drain tile and sand were placed in the 600 block and more concrete sidewalk and driveways were completed in the 400 & 500 blocks. Work also began between 8th Avenue and Irving Avenue with pavement milling and removals.

Next Week Look Ahead 9/7/2019-9/13/2019

The final lift of bituminous pavement is scheduled to be completed between Central Avenue and 4th Avenue NW today (9/6/19) and tomorrow (9/7/19) as well as paving in the driveways in the 400 and 500 blocks. The stripers are scheduled to be on site Monday (9/9/19) to place the permanent striping from Central Avenue to 4th Avenue NW and once the striping is done the signal systems at Central Avenue, 2nd Avenue and 4th Avenue will be placed into normal operations. Utility crews are scheduled to complete the remaining utility services and storm sewer in the 700 block and street crews should have the 600 block roadway complete through gravel. The electrician is scheduled to set more street lights and the concrete crews will continue filling in sidewalks, driveways and decorative concrete up to 6th Avenue NW. The contractor is also scheduled to complete the bituminous milling of TH 60 from Hulett Avenue to Irving Avenue on Tuesday (9/10/19) next week.

General Traffic Control/Detour Notes 

During the duration of the entire project and through the entire project limits which extend from Lyndale Avenue/TH 21 on the west end to Central Avenue on the east end, thru traffic will be detoured off TH 60 and rerouted along 2nd Avenue NW, TH 3/20th Street NW and TH 21 (see detour map link above) Portions of TH 60/4th Street NW within the project limits may be signed “Road Open to Local Traffic or Road Closed to Thru Traffic” or something similar. Please keep in mind that “local traffic/access” is defined as having direct access on TH 60, or having business with someone or a business who has direct access on TH 60. If you do not fall into either of these two categories, you should not be on TH 60 within the project limits at any time. Travel on TH 60 within the project limits should take place only when there is no other possible alternative. Also please be respectful of private property and do not use private property to “short cut” the detour route.

Pedestrian traffic will be maintained to the maximum extent practical to provide access to businesses and residents who have access to TH 60, however other portions of sidewalk will be closed to facilitate construction work and those sidewalks will be detoured along an alternate pedestrian route (typically around the block). Please review the link to the FAQ above for more information about access during construction.

For a full map of detours,  click here.  

Phase 1 (Central to Fourth) Access Notes: 

This area is open to traffic. The final lift of bituminous pavement is scheduled to be completed between Central Avenue and 4th Avenue NW today (9/6/19) and tomorrow (9/7/19) as well as paving in the driveways in the 400 and 500 blocks. The stripers are scheduled to be on site Monday (9/9/19) to place the permanent striping from Central Avenue to 4th Avenue NW and once the striping is done the signal systems at Central Avenue, 2nd Avenue and 4th Avenue will be placed into normal operations.

For a full map of detours and access maps, click here.

Phase II (Fourth to Sixth) Access Notes:

4th St NW/TH 60 is now closed from 6th Avenue to Irving Avenue for Phase 3 construction.

For a full map of detours and access maps, click here.

Phase III (Sixth to Irving) Access Notes:

4th St NW/TH 60 is now closed from 6th Avenue to 8th Avenue NW for Phase 3 construction. The intersection of 8th Avenue is expected to be closed September 5th or 6th for removals and utility work to proceed. 

For a full map of detours and access maps, click here.

About this update

The City of Faribault and its project partners intend to send out and publish a weekly construction update on the Trunk Highway 60/4th Street NW Reconstruction Project.  This weekly update will be issued through the City of Faribault Facebook page and the City’s website www.faribault.org  on the Project website http://www.ci.faribault.mn.us/549/2019-03-TH-60-Reconstruction.  You can sign up and receive an emailed PDF of the newsletter by submitting your email address to mduchene@ci.faribault.mn.us and requesting to be placed on the weekly TH 60 newsletter distribution list. You can also sign up for a text notification that will contain a link to the newsletter via the Faribault Chamber of Commerce by texting Faribault Hwy60 to 313131.  Questions about the contents of the weekly updates or about the project in general can be directed to Faribault City Engineer Mark DuChene at either 507.333.0360 or mduchene@ci.faribault.mn.us or to Glenn Cunningham, senior engineering technician, at either 507.333.0366 or gcunningham@ci.faribault.mn.us.   

Answers to many frequently asked questions (FAQ) about the project can be found here

The project is proposed to be completed in four main phases, and a copy of a map showing the project detour as well as project phasing and anticipated phasing timelines can be found here.

If there is a non-life threatening emergency within the construction limits (such as loss of water) outside of normal business hours, please call police dispatch at 507.334.4305 and they will contact the appropriate parties.  